Date: 20 Feb 2013
Location: CSR, Shah Alam
Job Scope: Lifting of 1 unit boiler and accessories to its designated position. Lifting to be carried out through a hole on the roof top. Roof is to be dismantle. Boiler is approximately 10 tons.
Location: CSR, Shah Alam
Job Scope: Lifting of 1 unit boiler and accessories to its designated position. Lifting to be carried out through a hole on the roof top. Roof is to be dismantle. Boiler is approximately 10 tons.
Crane parking position is restricted by the road width. Our crane needs at least 9m for its extension of outrigger but the road is only 7m. Therefore, alternate parking position is needed.
The alternate parking position is further away from the initial parking position. Which causes the working radius to be 24m instead of 10m.
Due to the increase in working radius a proposed 160ton crane is needed rather than the initial 80ton crane. The boiler will be lifted according to the diagrams above. It will be lifted from the transportation vehicle to the designated position over and above the pipe rack and then into the roof opening.
Walkie-talkie will be used for communication between rigger and crane operator.
Lifting will be carried out at a later date upon confirmation from customer.
Walkie-talkie will be used for communication between rigger and crane operator.
Lifting will be carried out at a later date upon confirmation from customer.